ARRA PROJECT (Stimulus Funds)
Salisbury Street (Robinson to Wiggins)
$252,000 Reith-Riley Construction
Asphalt patching, surface milling and asphalt overlay
Started – June 1
Complete By – June 30
2010 CDBG
Robinson Street (DeHart to Stadium)
$105,000 Jack Isom Construction
New concrete curbs and sidewalks, both sides of street.
Appx. Start Date – 6/21
Complete By – July 30
2010 STREET RESURFACING
Milestone Contractors (total contract - $674,487.50
Salisbury Street (Columbia to Wiggins) $23,000
Littleton Street (State to Dead End) $84,000
Littleton Street (Fowler to Quincey) $13,000
Maple Street (Quincey to Lutz) $58,000
Quincey Street (Salisbury to River) $153,000
2010 CRACK SEALING
Pavement Solutions (total contract - $67,979.39)
Grant Street (Meridian to Salisbury) – $12,000